In many places in Lithuania the distribution grid can no longer take more solar energy. The grid operator, ESO, then sets a low permitted export power: the number of kilowatts your system may send to the grid at any one time.
What a 1 kW export limit means
It is not a limit on the size of the system but on how much power you may export. The system itself can be larger, but everything above 1 kW that the home does not use must be stored, or the inverter will limit production.
What ESO says
- ESO has raised the power at which a system can be connected without obtaining technical conditions: from 0.8 kW to 1 kW.
- A solar system with a storage device and a 1 kW export limit can be connected without ESO technical conditions, under the standard connection terms.
- The customer only has to install the equipment; the contractor’s declaration is submitted through the ESO website.
What equipment you need
- A hybrid inverter that limits export to the grid and manages the battery.
- A battery that takes the surplus during the day and returns it to the home in the evening.
- Solar panels sized to how much electricity you use yourself.
We describe the inverter types separately: hybrid or grid-tied inverter.
An example from our warehouse
Energy-CORE is a high-voltage battery and, according to our product description, works with Solis inverters. You can work out the number of panels in the system sizing tool.
Funding for such a system
For systems with a battery whose export limit does not exceed 1 kW, the Lithuanian agency APVA has a separate funding measure. It requires a system of at least 5 kW and a battery of at least 10 kWh. Amounts and conditions: APVA funding for solar systems.
Please note: the Energy-CORE 9.6 kWh battery does not reach this 10 kWh threshold. If you plan to apply for funding, choose 12.8 kWh or larger.
Common questions
Can I raise the export limit later?
You need to contact ESO about the connection terms. Whether it is possible depends on the grid at your location. If you received APVA funding for a system with a battery, you must keep to the 1 kW limit for 2 years after the end of project funding.
Do I need a certified contractor?
Yes. The installation is declared to ESO by a certified contractor. You can buy the equipment yourself, but a contractor must install and declare it.
Information checked on 12 November 2026. The rules may change, so please check the ESO website before buying. Prices include VAT and may change.